'''Status of the main coil''' - update from Buckley Systems (8/22/17)
 +
 +
* Coil shipment delayed until end of November 2017 due to tooling modifications needed and company mis-calculation of total amount of copper needed
 +
 +
::* [http://www.vsl.cua.edu/cua_phy/images/1/12/J-lab_1.jpg Picture 1]
 +
 +
::* [http://www.vsl.cua.edu/cua_phy/images/f/fe/J-lab_2.jpg Picture 2]
 +
 +
::* [http://www.vsl.cua.edu/cua_phy/images/d/db/J-lab_3.jpg Picture 3]
 +
 +
::* [http://www.vsl.cua.edu/cua_phy/images/3/35/J-lab_4.jpg Picture 4]
 +
 +
 +
'''Status of the corrector coil''' - delivered and at JLab in test lab
 +
 +
 +
'''Status of yoke'''
 +
 +
* earlier drawings
 +
::* [http://www.vsl.cua.edu/cua_phy/images/4/4e/SweepMagnetWeight.pdf NPS magnet weight]
 +
 +
::* [http://www.vsl.cua.edu/cua_phy/index.php/File:48d48magnet.png BNL 48D48 dipole]

Latest revision as of 11:18, 23 August 2017

Frame

NPS frame design scaled from HyCal

Frame design drawing from HyCal

Magnet

Status of the main coil - update from Buckley Systems (8/22/17)

  • Coil shipment delayed until end of November 2017 due to tooling modifications needed and company mis-calculation of total amount of copper needed


Status of the corrector coil - delivered and at JLab in test lab


Status of yoke

  • earlier drawings