(Created page with "DETECTORS AT JLAB * Discussion of fire safety requirements and relocation of equipment from room 126 to semi-clean room * SP-11 aerogel tray ::* Walter's group constructed the ...") |
|||
Line 31: | Line 31: | ||
::* overall idea is to have an APD setup and then test it in a noise-controlled environment | ::* overall idea is to have an APD setup and then test it in a noise-controlled environment | ||
::* built an attenuator circuit since pulser (to LED) not reproducible | ::* built an attenuator circuit since pulser (to LED) not reproducible | ||
− | ::::* initially used resistors, but | + | ::::* initially used resistors, but ([http://www.vsl.cua.edu/cua_phy/images/5/5b/From.jpg the pulse coming from the LED Driver was having a lot of reflections (with the first circuit we tried -A voltage divider-) due to the difference in the impedance]). Next, did impedance matching, i.e. attenuate signal, but with same impedance as LED driver, cables, etc. (50 Ohm) |
− | ::* results are encouraging - questions about the change in offset with changes to circuit | + | ::* [http://www.vsl.cua.edu/cua_phy/images/b/ba/To.jpg results are encouraging] - the pulse is more decent and gives [http://www.vsl.cua.edu/cua_phy/images/3/32/Signal.jpg this signal]. The [http://www.vsl.cua.edu/cua_phy/images/6/6c/ADCSpectrum.png resulting ADC spectrum] |
+ | ::* action item: there were questions about the change in offset with changes to circuit that need to be checked | ||
Latest revision as of 11:20, 12 April 2017
DETECTORS AT JLAB
- Discussion of fire safety requirements and relocation of equipment from room 126 to semi-clean room
- SP-11 aerogel tray
- Discussion of further analysis of KPP run (golden run=488) - coordinate dependence looks good overall - a few distributions: Events x-y on aerogel surface, NPE y-dependence total sum, NPE x-dependence total sum
- run 488 used a 0.5% carbon target (see Dave Meekins notes on target specs)and the spectrometer was set for momenta of > 1 GeV/c
- Note that HMS and SHMS runs have different numbers in the Hall C logbook
- for the currently installed tray (n=1.015 aerogel) the threshold is 800 MeV this means that all particles are above threshold and PID cuts on calorimeter will not help
- Discussion of Marco's study of PMT gains - inconclusive for now.
- action item: check aerogel performance at next possible occasion, go >1500 HV for PMTs , performance should not change with gain - any setting should have the same #p.e.
- Discussion about temperature control system for NPS prototype tests
- chiller selection
- Silviu has a program to generate temperature profiles - requires input like material, conductivity
- discussion about optical isolation of individual crystals in full NPS: tedlar affects conductivity, aluminum could damage the crystal and would have to be very thin
PBWO4 STUDIES AT CUA
- Prototype assembly (Richard)
- APS-based readout (Andres)
- overall idea is to have an APD setup and then test it in a noise-controlled environment
- built an attenuator circuit since pulser (to LED) not reproducible
- initially used resistors, but (the pulse coming from the LED Driver was having a lot of reflections (with the first circuit we tried -A voltage divider-) due to the difference in the impedance). Next, did impedance matching, i.e. attenuate signal, but with same impedance as LED driver, cables, etc. (50 Ohm)
- results are encouraging - the pulse is more decent and gives this signal. The resulting ADC spectrum
- action item: there were questions about the change in offset with changes to circuit that need to be checked
TIMELIKE COMPTON SCATTERING (Vardan)
- Figure Of Merit comparison between what can be achieved with NPS/HIPS in Hall C and HDICE in Hall B
- TCS HC seems comparable with HDICE
- Next: get an independent evaluation of the analysis
NEXT MEETING: WED 12 APRIL at 10:00 AM (EDT)